[Scheduled] Cloud | Luxembourg | Compute - Electrical power upgrade
Scheduled Maintenance Report for Gcore
Completed
The scheduled maintenance has been completed.
Posted Mar 28, 2024 - 19:00 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 28, 2024 - 05:00 UTC
Scheduled
Start: 28/03/2024, 05:00 UTC
End: 28/03/2024, 19:00 UTC
---
During this time period, our data center provider will be performing electrical power upgrade. No impact expected. We apologize for any inconvenience this may cause.

Data Center Plan:
05:00 Progressive shutdown of power Feed A and smooth transition of cooling to Feed B
08:00 Start of effective upgrade & maintenance works
Disassembling of electrical switchboard cells 3 and 4 in TGBT UPS A2
Replacement of 16 major power breakers >2000 A
Discrimination verification on breakers
Maintenance and cleaning of main electrical switchboards
17:00 End of effective upgrade & maintenance works
17:45 Progressive power up of critical customer load on Feed A
Posted Mar 20, 2024 - 18:31 UTC
This scheduled maintenance affected: Cloud | Luxembourg-1 (Compute - Instances, Baremetal) and Cloud | Luxembourg-2 (Compute - Instances).